Dartford, Kent

Client - Europa Worldwide Group

Value -

Duration - 12 weeks completed in 11 weeks

What we did:

Acted as the principal and groundworks contractor.

Broke out a large area of the external concrete yard.

Piling work for column bases.

Reinstated brush finished concrete slab.

Oversaw steel frame and cladding work.

Finished a week ahead of schedule. The client also awarded us a project in Bristol as a result.